AI- 9013   4. A. 4.    
Commissioners Court - Regular
Meeting Date: 11/29/2017  
Padre Balli Park Improvements, Phase 1 Change Order No. 8
Submitted By: Monica Rodriguez, Coastal Parks
Department: Coastal Parks  

Information
RECOMMENDATION
Discuss and consider the approval of Change Order No. 8 with TBC Commercial Construction to increase the contract amount relating to the Padre Balli Park Improvements, Phase 1 Project.
BACKGROUND
On February 24, 2016, Nueces County entered into a contract with TBC Commercial Construction LLC for the Padre Balli Park Improvements, Phase 1 Project (IFB NO. 3004-15)
DISCUSSION
Change Order No. 8 compensates the contractor, $17,986.68 for additional insurance costs due to delays encountered and the increase in contract time during the construction of this project.  Additional time (Change Order 7) was previously approved in court.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available:
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1:
Fund Transfers

Attachments
TBC Construction Change Order No. 8 & Form 1295