AI- 8921   4. A. 5.    
Commissioners Court - Regular
Meeting Date: 11/01/2017  
Padre Balli Park Improvements, Phase 1 Change Order 7
Submitted By: Monica Rodriguez, Coastal Parks
Department: Coastal Parks  

Information
RECOMMENDATION
Discuss and consider the approval of Change Order No. 7 to add a 45-day extension of time to the contract for TBC Commercial Construction LLC.
BACKGROUND
This contract is for the Padre Balli Park Improvements, Phase 1 and will expire on October 19, 2017.
DISCUSSION
Due to many problems encountered during the construction phase of this project, it will be necessary to add a 45-day extension to ensure the project is complete to a level that is acceptable to Nueces County.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available:
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1:
Fund Transfers

Attachments
TBC Change Order #7
Form 1295 - TBC Change Order #7