AI- 8649   4. D. 5.    
Commissioners Court - Regular
Meeting Date: 07/26/2017  
Change Order No. 1 for the ADA Modifications - Calderon Building
Submitted By: Irma Weaver, Public Works
Department: Public Works  

Information
RECOMMENDATION
Discuss and consider the approval of Change Order No.1 for the ADA Modification at the Calderon Building.
BACKGROUND
On April 12, 2017, Nueces County entered into a contract with D&SS Construction, Inc. for the construction of the ADA Modifications - Calderon Building.
DISCUSSION
Change Order No. 1 provides for the modification of existing concrete, electrical, plumbing, HVAC, ramp railing, city sidewalk and asphalt parking lot to allow proposed construction to continue and comply with ADA requirements.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available:
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1:
Fund Transfers
Fiscal Impact:
$24,917.55 (Project Funding: 19212003 - Calderon Bldg. ADA Improvements