Bishop Community Center Improvements Change Order No. 2
Submitted For: Joe A. Gonzalez Submitted By: Sandra Santos, Commissioner Pct 2
Department: Commissioner Pct 2  

Information
RECOMMENDATION
Discuss and consider the approval of Change Order No. 2 with A. Ortiz Construction & Paving, Inc., to increase the contract amount related to the Bishop Community Center Improvement Project to meet ADA Requirements.
BACKGROUND
On February 1, 2017, the Commissioners Court entered into a contract with A. Ortiz Construction & Paving, Inc. for the Bishop Community Center Improvement Project for $113,782. Change Order No. 1 added an additional 30 days and added the amount of $11,145.00.
DISCUSSION
Change Order No. 2 will add an additional cost of $4,083.20 for necessary labor and material to meet ADA requirements and will include the removal of 30 s/f of concrete sidewalk, extend proposed ramp, add an additional 124.4 s/f of landing plus 2 additional hand railing curves at rear exits of building. Adjusted contract amount: $129,010.20. This change order will be paid out of Bishop Community Center ADA Improvements, Project Code 19212010.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available:
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1:
2: 19212010
Fund Transfers
Source of Funds: Captial Project ADA Improvements Amount Requested: 4083.20 Fiscal Year: Budgeted Y/N: Y
Fiscal Impact: