Print PDF Return
AI- 8529   4. B. 2.    
Commissioners Court - Regular
Meeting Date: 06/21/2017  
Supplemental Agreement No. 1 for an Engineering Services Contract with Hanson Professional Services, Inc.
Submitted By: Irma Weaver, Public Works
Department: Public Works  

Information
RECOMMENDATION

Discuss and consider the approval of Supplemental Agreement No.1 for an Engineering Services Contract with Hanson Professional Services, Inc., related to the County Road 52 Extension Project.

BACKGROUND
On July 8, 2015, Nueces County entered into an Engineering Services Contract with Hanson Professional Services, Inc. (formerly Naismith Engineering) for the preparation of plans, specifications, and construction phase services associated with the County Road 52 Extension Project.
DISCUSSION
Supplemental Agreement No. 1 provides for additional compensation due to change in scope that included surveying, drainage assessment, roadway assessment, and repair coordination for a section.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available:
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1:
Fund Transfers

Attachments
Supplemental Agreement No. 1
Engineering Services Contract
Assignment Agreement
Revised Attachments B, C, & D
Form 1295