AI- 8160   4. A. 4.    
Commissioners Court - Regular
Meeting Date: 02/01/2017  
Padre Balli Park Improvements, Phase 1 Change Order No. 3
Submitted By: Monica Rodriguez, Coastal Parks
Department: Coastal Parks  

Information
RECOMMENDATION
Discuss and consider the approval of Change Order No. 3 with TBC Commercial Construction LLC, to increase the contract amount relating to the Padre Balli Park Improvements, Phase 1 Project.
BACKGROUND
On February 24, 2016, Nueces County entered into a contract with TBC Commercial Construction LLC for the Padre Balli Park Improvements, Phase 1 Project (IFB NO. 3004-15).
DISCUSSION
Change Order No. 3 compensates the contractor, $102,900.00 to turn the existing (44) patios into concrete.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available:
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1:
Fund Transfers
Source of Funds: 19197001 Amount Requested: $102,900.00 Fiscal Year: Budgeted Y/N:
Fiscal Impact:

Attachments
TBC Construction LLC Change Order No. 3