BACKGROUND
Scope of work for this project consist of constructing approximately 3,908 square feet of concrete walking trail, three (3) concrete exercise stations, crosswalk striping, and a timber pavilion with concrete foundation and four (4) timber benches.
DISCUSSION
Five bids were received. Mo-Con Construction's failed to bid the complete scope of work and the bid is disqualified.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available:
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1:
Fund Transfers

Attachments
IFB 3031-16 bid tab

AgendaQuick©2005 - 2020 Destiny Software Inc., All Rights Reserved