Change Order No. 2 Terry Shamsie Boulevard Reconstruction
Submitted By: Yolanda Moreno, Public Works
Department: Public Works  

Information
RECOMMENDATION
Approve Change Order No. 2 for the Terry Shamsie Boulevard reconstruction.
BACKGROUND
On August 3, 2016, Nueces County entered into a contract with JE Construction Services for the construction of the Terry Shamsie Boulevard reconstruction.
DISCUSSION
Change Order No. 2 provides an improved left turn radius at the east end of Terry Shamsie Boulevard. The deletion of an island with pavers and a reduced length of the median. Also, a length of curb and median that has been placed will be demolished. Additionally, this revision adds curb in two areas and includes minor grading.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available:
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1:
Fund Transfers
Source of Funds: 19196003 Amount Requested: Fiscal Year: Budgeted Y/N:
Fiscal Impact:
None ($0.00)

Attachments
Change Order No. 2 Terry Shamsie Blvd. Reconstruction