Print PDF Return
AI- 7574   4. D. 1.    
Commissioners Court - Regular
Meeting Date: 08/17/2016  
Hazel Bazemore Park Ravine Stabilization Change Order No. 1
Submitted By: Yolanda Moreno, Public Works
Department: Public Works  

Information
RECOMMENDATION
Discuss and consider the approval of Change Order No. 1 with MO-CON Services, Inc., to increase the contract amount relating to the Hazel Bazemore Park Ravine Stabilization Project.
BACKGROUND
On February 24, 2016, Nueces County entered into an contract with MO-CON Services for Hazel Bazemore Park Ravine Stabilization Project.
DISCUSSION
Change Order No. 1 compensates the contractor $8,583.00 for additional installation of granite slab and will credit Nueces County {$1,532.20} for line item Rock Filter Dam (Remove) which will not be used.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available:
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1:
Fund Transfers
Source of Funds: 19012100-Hazel Bazemore Clean-up Amount Requested: Fiscal Year: Budgeted Y/N:
Fiscal Impact:
$7,050.80 19012100-5312

Attachments
Mo-Con Services Change Order No. 1
Form 1295

AgendaQuick©2005 - 2020 Destiny Software Inc., All Rights Reserved