AI- 4628   4. A. 4.    
Commissioners Court - Regular
Meeting Date: 09/18/2013  
Bob Hall Pier Kitchen Renovations - IFB 2923-12 - Change Order No. 3
Submitted By: Monica Rodriguez, Coastal Parks
Department: Coastal Parks  

Information
RECOMMENDATION
Discuss and consider approval of Change Order No. 3 for an increase of $9,199.38 to HSC Electric Company for Bob Hall Pier Kitchen Renovations.
BACKGROUND
On March 13, 2013 Nueces County entered into a contract with HSC Electric Company for renovations at the existing Bob Hall Pier Concession Bldg.  Change Order No. 1 for $22,920.60 was approved at Commissioners Court on April 30, 2013.  Change Order No. 2 for $10,000.00 was approved at Commissioners Court on July 24, 2013. 
DISCUSSION

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available:
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1:
Fund Transfers
Source of Funds: 2004 CO's Amount Requested: $9,199.38 Fiscal Year: FY 12/13 Budgeted Y/N: Y
Fiscal Impact:
Bob Hall Pier Kitchen Renovation
Project 19152812

Attachments
Bob Hall Pier Renovation - CO #3