AI- 3516   4. D. 1.    
Commissioners Court - Regular
Meeting Date: 07/25/2012  
McKinzie Jail Annex HVAC Rehabilitation - Change Order No. 7
Submitted By: Mario Garza, Public Works
Department: Public Works  

Information
RECOMMENDATION
Discuss and consider approval of Change Order No. 7 for the McKinzie Jail Annex HVAC Rehabilitation Weathertrol, Inc. project.
BACKGROUND
On March 3, 2010 Nueces County entered into a contract with Weathertrol, Inc. for the McKinzie Jail Annex HVAC Rehabilitation.
DISCUSSION
This change order adds to the Structural and Windstorm Certification allowance amount of $18,000.00 allotted in the plans. The actual construction cost expended by the contractor for Structural and Windstorm Certification is in the amount of $25,440.34.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available:
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1:
Fund Transfers
Fiscal Impact:
$7,440.34*

*Transfer $7,440.34 from project 19177004 (Juvenile Justice Center Chiller Replacement) to project 19174001 (McKinzie Jail Annex HVAC Rehabilitation)